Advanced Simulation and Computing Program, ASC
CONTACTS
|
ASC Platform Installation: Roadrunner Arrives at Los Alamos
IBM and LANL Team at IBM's Poughkeepsie plant where Roadrunner achieved a sustained petaFLOPS, or 1.026 petaFLOPS, in May 26, 2008.
Moving the first Connected Unit (CU) into the Metropolis Center for Modeling and Simulation The first Roadrunner Phase 3 Connected Unit (CU) was delivered to Los Alamos on July 15, 2008. Shortly after delivery, IBM successfully kicked off a Linpack burn-in run on the first CU in the Metropolis Center for Modeling and Simulation. LANL will begin acceptance testing this month. In January 2009, the file systems will be connected and scientists will begin system and code stabilization using weapons and open-science code runs. This installation is very exciting because of the potential for advancing science and engineering toward predictive capabilities for the ASC stockpile stewardship mission and other national needs.
|